Street Seal Program

Adams County Government is committed to providing a website that is accessible to the widest possible audience and advancing technology accessibility in all our county information and communication technology (“ICT”). We are actively working to increase the accessibility and usability of our ICT in accordance with Colorado Laws For Persons With Disabilities, HB 21-1110, as amended, and the rules promulgated by the Office of Information Technology of the State of Colorado. To view our accessibility statement, please click here.

Project Overview

This Adams County project focuses on improving various paved streets identified as priorities for a seal treatment. Seal treatments extend the life of paved roads. Two different types of treatments are used slurry seals and chip seals.

  • Slurry seal is applied in order to help preserve and protect the underlying pavement structure and provide a new driving surface. Roads chosen for slurry seal applications generally have low to moderate distress and narrow crack width.
    • Day 1 (9-18-25): Riverdale Rd.
    • Day 2 (9-19-25): 136th Ave., Boston St., E 138th Ct., E 139th Ct.
    • Day 3 (9-22-25): Quince St., Bachman Dr., E 123rd Dr., E 123rd Cir., Monaco Way, E 123 Rd. Pl., Newport Ct.
    • Day 4 (9-23-25): Newport Dr., Niagara Ct., Magnolia Way, Monaco Dr., E 120th Pl., E 120th Dr.
    • Day 5 (9-24-25): E 123rd Dr., Ivy Pl., E 124th Way, Ivehoe St., Niagara St.
    • Day 6 (9-25-25): Krameria St., E 122nd Dr., E 122nd Ave., E 121st Pl., E 121st Dr., Ivy Cir., E 121st Pl., E 120th Pl.
    • Day 7 (9-26-25): Locust St., E 123rd Ave., E 123rd Pl. E 123rd Dr., Kearney St., Ivy Way, Ivy Ct., Ivanhoe Ct., Holly Way
    • Day 8 (9-29-25): E 123rd Ave., 76th Ave.
  • Chipseal (also chip seal) is a pavement surface treatment that combines one or more layer(s) of asphalt with one or more layer(s) of fine aggregate.
    • 9-10-25: Riverdale Rd.
    • 9-11-25: 136th Ave., Boston St., E 138th Ct., E 139th Ct.
    • 9-12-25: Quince St., Bachman Dr.
    • 9-15-25: E 123rd Dr., E 123rd Cir., Monaco Way, E 123rd Pl., Newport Ct.
    • 9-16-25: Newport Dr., Niagara Ct., Magnolia Way, Monaco Dr., E 120th Pl., E 120th Dr.
    • 9-17-25: E 123rd Dr., Ivy Pl., E 124th Way, Ivehoe St., Niagara St.
    • 9-18-25: Krameria St., E 122nd Dr., E 122nd Ave., E121st Pl., E 121st Dr., Ivy Cir., E 121st Pl., E 120th Pl.
    • 9-19-25: 76th Ave.

The project encompasses two different areas in the county, see map below for details:

2025 Street Maintenance | CIP & Street Maintenance Experience

Work will begin mid-August through end of October.

Contact Information

If problems or concerns arise that the Contractor is not resolving, please contact the Adams County Infrastructure Manager at 720.523.6840.